Phase I:
-
Internal Modification of the prayer area which will include:
-
Construction of six bathrooms (three for men and three for women) along with Wudu areas.
-
Water drinking fountains in men and women prayer areas
-
Converting the existing bathroom into an office.
-
Installing carpeting throughout prayer area.
-
Modification of the Masjid’s frontage.
-
Complying with all ADA requirements.
-
Connect into the sewer system and abandon the existing septic system.
-
Parking lot & landscaping:
-
54 parking spaces including spaces for handicap parking.
-
8670 sq. ft. of landscaping.
-
Parking lot and exterior site lighting system consisting of 16 stations.
-
Electric vehicle charging station.
-
Refuse containers enclosure.
-
Street improvements:
-
Sidewalk and street re-pavement
-
Street Lighting
-
26’ wide X 46’ long main entrance driveway.
-
Fencing and gates:
-
200 feet of 6-foot high masonry wall along the Eastern boundary of the property.
-
200 feet of 6-foot high wrought iron fence along the front of the property.
-
26 foot sliding gate (electrically-operated) for the main entrance.
-
5-foot gate for pedestrians to access the Masjid from the sidewalk.
-
4-foot gate for pedestrians to access the parking lot.
Phase II:
-
Minaret:
A 35-foot minaret will be constructed in the area designated as a 1550 sq. ft. landscaped section just south of the prayer hall.
-
Steel Structure Remodeling:
The existing steel structures will be converted into a 2500 sq. ft. multipurpose hall.
Related Documents:
Schedule of Construction:
We are currently in the process of obtaining the building permits to start undertaking the first phase of the development. The completion of Phase I first two projects is expected by the second quarter of 2015. While we expect to complete Phase I projects 3, 4 and 5 by the 1st quarter of 2016, it is estimated that the cost of Phase I five projects will be about $300,000. We currently have $130,000 of available funds and are in need of $170,000 of additional funds to complete Phase I.
As for Phase II, insha’allah, we hope to begin undertaking its two projects as soon as we complete the required Phase I projects. We estimate the two projects will cost $320,000 (in today’s dollars).
Appeal For Financial Support:
We ask for your help to insure that we accomplish our ambitious goals in a timely basis. You can make your tax-deductible donations either using a credit or a debit card, or by sending your check, or money order to the Center’s address: 18027 Sierra Highway, Canyon Country, CA 91351.
Regards,
Board of Directors
Al-Umma Center of Santa Clarita Valley